They're calling it a "solar farm." It's a 100 MW industrial power plant — up to 923 acres of arrays planned across the working fields of Watertown, Ixonia & Concord — and three commissioners in Madison decide, not us.
Every number below comes from the developer's own application to the Wisconsin Public Service Commission — Docket 9823-CE-100.1
A merchant-scale generating facility — not a family farm, not community solar.1
Land the developer holds rights to across three townships — down from a 2,104-acre study area, still three square miles of our county.1,2
558 "primary" acres plus 365 more the developer reserves as "alternative" array sites — plus ~110 acres of substation, roads and gen-tie.1,2
34.5 kV circuits trenched under the fields, feeding a new 138 kV substation.1
In development since 2018; the developer targets an in-service date of December 2028.1,2
Towns of Watertown, Ixonia & Concord. Farmington was in the original application and has since been dropped.1,2
Same land. Same horizon. One of these grows food and holds our rural character — the other is up to 923 fenced acres of graded dirt, steel piles and glass. This is what construction actually looks like.
Once the fences go up, it isn't a farm anymore. Slide to compare.
Eight documented, evidence-based reasons Jefferson County neighbors are demanding a real seat at the table.
The American Farmland Trust projects that of ~7 million acres of new U.S. solar by 2040, about 83% could land on agricultural land. Developers hunt flat, dry, cleared fields near power lines — the exact traits that make prime farmland.
American Farmland Trust, "Farms Under Threat 2040" (projection)4
Approval rests with three state commissioners in Madison. And under Wis. Stat. § 196.491, because it's a merchant plant selling into the wholesale market, the Commission is barred from even reviewing whether we need the power.
Wis. Stat. § 196.491; WI Legislative Council memos5
A 2025 PNAS study of 8.8 million home sales and 3,699 solar sites found residential homes within three miles of large-scale solar lost 4.8% of value on average — a "stigma" cost borne by neighbors who never signed a lease.
Chen, Hu & Liu, PNAS 2025 · DOI 10.1073/pnas.24184141226
A 2025 review in Renewable & Sustainable Energy Reviews found solar sites drive habitat loss and fragmentation, and perimeter fencing blocks the corridors animals travel. Residents have also flagged bald eagle nesting — a federally protected species — in the project area.
Fleming et al., 2025 · DOI 10.1016/j.rser.2025.115995 · PSC comment record7,3
Solar has a ~30-year life, and restoration means removing all below-ground structures, de-compacting soil and restoring drainage tile. Who does that in 2058 if the developer is bankrupt? Decommissioning bonds exist precisely because that risk is real.
Kleinman Center (UPenn); NC DEQ; DSIRE Insight8
This isn't solar vs. no solar — it's siting. NREL found U.S. rooftops alone could supply ~39% of the nation's electricity, and the DOE and EPA push solar onto 450,000+ brownfields and landfills. The land to hit clean-energy goals exists. Prime Jefferson County cropland doesn't have to be it.
NREL rooftop assessment; DOE/EPA RE-Powering9
The FCC just added foreign-made power inverters to its national-security Covered List (July 2026), citing risks of remote disabling of infrastructure — after Reuters found undocumented communication devices hidden in Chinese-made inverters. Sinnissippi's application names only example equipment, has signed no supply agreements, lists Chinese module makers as candidates — and nothing requires it to disclose country of origin before energizing 100 MW next to our homes.
FCC Covered List action, July 2026; Reuters, May 2025; Sinnissippi CPCN application10,11,12
The state's preliminary determination says the project needs no full Environmental Impact Statement — yet the same assessment admits construction brings noise, dust and vibration for residents, soil erosion and runoff, and that "some animals may be displaced." Residents have documented numerous bald eagle nesting sites in the project area. An 1,944-acre project deserves the full study. Tell the PSC so — comments are due August 28.
PSC preliminary determination & Environmental Assessment, Aug 2026; docket comment record2,3
Public comment is our best remaining window. Here's where we are.
Invenergy starts signing landowner leases across the towns.2
Sinnissippi Solar Energy LLC asks the PSC for a Certificate of Public Convenience and Necessity — Docket 9823-CE-100. A revised application follows in March 2026.1
Hundreds of comments flood the docket. The Town of Farmington comes OUT of the project footprint, and the land under developer control shrinks from 2,104 to 1,944 acres. Pressure changes this project.2,3
The PSC's preliminary determination (Aug 4) would let the project skip a full Environmental Impact Statement. Comments on that determination are due Friday, August 28, 2026. This is the window.2
Vegetation removal, grading, pile-driving and 25 miles of trenching begin across the project area.1
Developer target in-service date. Once built, there is no guarantee the soil is restored to prime cropland.1,2,8
We do not have a public copy of any landowner lease, and we will not guess what yours says. Only a Wisconsin attorney who has read your signed document can tell you what options, if any, apply to you.
Keep the full document — not a brochure, not a verbal summary, not what a neighbor remembers. If you cannot find it, ask the company in writing for a complete copy and keep that request.
Have independent Wisconsin counsel review your specific agreement before you act, decline to act, or sign anything else. Do not rely on the company's explanation of your paperwork.
If your attorney identifies a notice, deadline, or other step in your agreement, follow that instruction exactly and keep dated proof. We cannot name those terms from this page.
This is not legal advice. We are a neighborhood coalition. We do not interpret private contracts.
If you signed and want to talk with neighbors — without us claiming what your paperwork says — reach out. We can help you find independent counsel. We will not tell you what is in your lease.
Jefferson County's identity is farms, woodlots and open horizons — not chain-link fence and glass as far as you can see.
Habitat fragmentation, blocked corridors and protected species deserve real, site-specific study — not boilerplate.
Trenching 25 miles of cable disturbs ground that may hold Native American and historical resources. Survey first.
Construction traffic, inverter and substation noise, dust and night lighting — imposed on families who never signed a lease.
Your biggest investment shouldn't lose value because Madison approved your neighbor's lease. Towns deserve a binding voice.
Then you belong in this fight. It takes 30 seconds to add your name.
Sign the petitionFile a comment on PSC Docket 9823-CE-100 by August 28, then write your town board, county supervisors, legislators and the DNR. We built you the full directory — every name, phone and link.
Open the contact directory →Town board, county Planning & Zoning, and the upcoming PSC public hearings. A full room changes outcomes — we'll tell you when and where.
Get meeting alerts →Host a yard sign, knock doors, gather petition signatures or help with research. Every hour moves the needle.
Raise your hand →Start with the PSC comment: that's the official record the commissioners must read. Then make it personal — your town board and legislators answer to you.
The Public Service Commission is weighing this project right now. Your name, your comment, and your presence at one hearing may be the difference for the next generation of Jefferson County.